WPS-IEW-2026-105

Rev. 0NON_COMPLIANTIBRBoiler Manufacturing

SAW longitudinal seam, boiler drum shell course 50 mm (PWHT pending review)

Bharat Heavy Electricals Ltd., Trichy Er. S. Venkataramanupdated 15 Feb 2026, 09:30 pm

97

score

Edit Audit Report

Base Metals & Thickness — QW-403 / QW-451

Specification
SA-516 Gr.70 (IBR Form IV-A)
P-Number
P-No. 1
Group No.
2
Dissimilar side
Same P-No.
Qualified range
50 – 100 mm
Coupon T
50 mm
Diameter
Shell ID 1600 mm
Toughness
Not invoked

Filler Metals — QW-404 / QW-432 / QW-442

Filler spec
SFA-5.17 + flux IS:3613
Classification
EM12K + F7A4-EM12K flux
F-Number
F-No. 6
A-Number
A-No. 1
Process
SAW
Transfer mode
—
Joint type
Single-U Groove
Position
1G

Thermal Cycle — QW-406 / QW-407

Preheat min
150 °C
Interpass max
280 °C
PWHT
Not required
PWHT soak
—
PWHT hold
—
Joint design
Single-U, R=8 mm root radius, backing run SMAW from ID

Electrical, Technique & Shielding — QW-408 / QW-409

Current
DCEP
Amperage
550–750 A
Voltage
28–34 V
Travel speed
400–550 mm/min
Heat input cap
4 kJ/mm
Shielding
N/A (flux)
Flow
—
Backing
—
Supporting PQR
PQR-IBR-2026-105

Validation Findings

latest run 15 Feb 2026 by welding.engg@bhel.in

FAIL

Mandatory PWHT by thickness/code

EssentialReg. 273

PWHT is mandatory: P-No. 1 at 100 mm exceeds the 30 mm threshold for boiler/IBR construction.

Supporting PQR referenced

EssentialReg. 274

Qualified by PQR PQR-IBR-2026-105. Traceability established.

Base metal P-Number assigned

EssentialReg. 261

Base metal group P-No. 1 Gr.2 — SA-516 Gr.70 (IBR Form IV-A).

Dissimilar-metal weld compatibility

EssentialReg. 268

Joint is between identical P-Numbers — no dissimilar-metal restrictions apply.

Thickness qualification range (coupon)

EssentialReg. 271

Range 50–100 mm within qualified 1.5–100 mm for 50 mm test coupon.

Thickness range sanity

Non-EssentialReg. 271

Commercial range 50–100 mm is within conventional procedure limits.

Small-bore thin-wall root control

Non-EssentialReg. 267

Small-bore root check applicable to piping only.

Minimum preheat temperature

EssentialReg. 266

Preheat ≥ 150°C satisfies the 65°C minimum for P-No. 1 base metal.

Interpass temperature ceiling

EssentialReg. 266

Interpass 280°C within 315°C ceiling.

Thermal window logic

Non-EssentialReg. 266

Thermal window 150–280°C is internally coherent.

PWHT cycle parameters

EssentialReg. 273(3)

PWHT not required — cycle parameters not applicable.

PWHT soak window & hold adequacy

Suppl. EssentialReg. 273(4)

PWHT not required — soak band check not applicable.

F-Number consistent with process

EssentialReg. 264

F-No. 6 (EM12K + F7A4-EM12K flux) is consistent with SAW.

Weld-metal A-Number compatibility

EssentialReg. 264

A-No. 1 weld deposit is chemically matched to P-No. 1.

Shielding gas / medium per process

EssentialReg. 265

SAW is flux-shielded; external shielding correctly marked N/A.

Root backing gas protection

Suppl. EssentialReg. 265

SAW — backing gas not driven by process.

Shielding gas flow rate

Non-EssentialReg. 265

Flux process — flow rate not applicable.

Current type & polarity

EssentialReg. 265

DCEP polarity consistent with SAW and EM12K + F7A4-EM12K flux.

Amperage operating window

Non-EssentialReg. 265

Amperage 550–750 A inside the SAW operating envelope.

Arc voltage operating window

Non-EssentialReg. 265

Voltage 28–34 V inside the SAW operating envelope.

Travel speed control

Non-EssentialReg. 265

Travel speed 400–550 mm/min is plausible for SAW.

Heat input ceiling (toughness)

Suppl. EssentialReg. 266

Computed worst-case heat input ≈ 3.83 kJ/mm (declared ceiling 4 kJ/mm) — no toughness restriction invoked.

Welding position qualification

Non-EssentialReg. 272

Position 1G is a recognised EN ISO 6947 / QW-461 designation.

GMAW metal-transfer mode

EssentialReg. 265

Transfer-mode variable applies to GMAW only (SAW exempt).

Process admissibility under code

EssentialReg. 263

SAW is an admissible process under IBR.

ISO 15614 impact-test mandate

Suppl. EssentialReg. 270

Impact regime not invoked for the declared thickness/application.

Storage-tank qualification route

Essential—

Tank-specific routing not applicable.

IBR statutory governance

EssentialReg. 274–283 / Ch. XIII

Prepared by Er. S. Venkataraman; welder must hold a valid IBR welder's certificate and records are subject to Inspecting Authority countersignature (Reg. 277–283).

Administrative data completeness

Non-EssentialReg. 274

Administrative header fields adequately populated for issue.

Group Number under toughness

Suppl. EssentialReg. 261

Group-No. split applies only when notch toughness is specified.

Run History

welding.engg@bhel.in

15 Feb 2026, 09:30 pm

FAIL

29/0/1